Skip to Content Skip to Search Skip to Left Navigation U.S. Department of Transportation (US DOT) Logo Research and Innovative Technology Administration (RITA) Logo RITA - ITS Professional Capacity Building Program
  ABOUT RITA | CONTACT US | PRESS ROOM | CAREERS | SITE MAP
Bureau of Transportation Statistics
Intelligent Transportation Systems
About the Program
News
Learn About Standards
Background
Research Initiatives
Application Areas
National ITS Architecture
Standards Lifecycle
Standards Development
Standards Testing
Systems Engineering
Final Rule/Policy
Common Questions
Acronyms
Glossary
Deployment Resources
Development Activities
Links
Contacts
Site Map
ITS Standards Home
National Transportation Library
Research Development & Technology
Transportation Safety Institute
University Transportation Centers
Volpe National Transportation Systems Center


ITS Standards Program

SEARCH STANDARDS

Systems Engineering

ITS Standards in the Systems Engineering Process

ITS Standards are primarily used in the design stage of the systems engineering process, after a high-level design (project architecture) has been developed. During the detailed design phase, specific messages, data elements, communications profiles, and design options are defined.

Systems Engineering is a process-oriented means of deploying a system that leads to reduced risk, controlled cost and schedule, improved system quality, and a resultant system that meets user needs.

There are multiple ways to represent the systems engineering process. One way, the Systems Engineering "V" Diagram (see figure below), represents the typical life cycle of any system or project. Whether the system being deployed consists of a basic computer-aided dispatch (CAD) system for a transit agency, or a more complex interface between a traffic management center and a public safety agency, all systems will follow some variation of this life cycle.

Where We Are in the Systems Engineering Life Cycle.  Text immediately following graphic explains the seven stages depicted

Stage 1: Concept of Operations — The manner in which the system will be used is defined.

Stage 2: Requirements — High level and detailed requirements define what the system will do.

Stage 3: Design — High-level and detailed specifications define how the system will meet the requirements.

Stage 4: Implementation — The components are built or deployed.

Stage 5: Integration & Testing — As each component of the system is completed, it is integrated into the overall system and tested to ensure that the specifications are satisfied.

Stage 6: System Verification — Also called acceptance testing, this step ensures that the overall system is consistent with the design, and that it meets the requirements.

Stage 7: Operations & Maintenance — This stage represents the ongoing process of using the system in the manner in which it was intended (and validating that it can be used in this way) and maintaining the system.

The systems engineering process is used during the development of ITS standards, as well. Some standards include sections which document this process to help ITS deployers with interpreting and using the standard. For example, the concept of operations developed for an ITS standard may help ITS project designers to conceptualize how messages might be exchanged between systems, such as the order in which control information is sent to a field device and the type of status returned. Additionally, the high-level and detailed requirements developed for an ITS standard might be used to create system functional requirements that could also be used later during system verification.

Learn More